In Singapore, Periodic Façade Inspection (PFI) applies to buildings that are more than 20 years old and more than 13 metres tall, unless excluded under the regulations. Once a building is due for inspection and BCA issues a PFI notice, the building owner must appoint a Competent Person to carry out the inspection and submit a façade inspection report.
A facade inspection report records the building’s façade condition, inspection methodology, evidence collected, defect locations, condition assessment, recommended follow-up actions, and Competent Person certification. It should include the full visual inspection, close-range inspection covering at least 10% of the surface area of each elevation, photo evidence, defect mapping, condition classification, repair recommendations, and final endorsement by the Competent Person.
The report is important because façade defects affect both public safety and owner accountability. Loose panels, falling tiles, cracked concrete, failed fixings, corrosion, displaced elements, and deteriorated façade materials can create safety risks for pedestrians, occupants, and neighbouring properties.
A good report does more than record defects. It helps owners understand repair priorities, plan corrective works, maintain a clear audit trail, and comply with regulatory requirements.
This guide explains what goes inside a facade inspection report, who prepares it, how evidence is collected, how findings are classified, and what building owners should prepare before inspection.
Quick Summary
- A PFI report should document inspection coverage, mapped defects, photo evidence, condition classifications, repair recommendations, and Competent Person certification.
- Findings are classified as Safe, Require Repair, or Unsafe, with the required repair action, precautions, and timeframe clearly stated.
- Owners should keep the report with repair records to track completed work and compare conditions during the next inspection cycle.
What Is a Facade Inspection Report?
A facade inspection report is the formal document prepared after a Periodic Façade Inspection. It is prepared and endorsed by the Competent Person appointed by the building owner to inspect and assess the façade condition.
The report should include façade photos, inspection dates, areas checked, inspection methods, tools used, photo references, defect locations, condition assessment, and the Competent Person’s professional conclusion.
The report should classify the condition of each façade type or façade system as Safe, Require Repair, or Unsafe. For façade areas classified as Require Repair or Unsafe, the report should clearly identify the defect locations, descriptions, evidence, likely causes where relevant, and recommended repair or precautionary measures.
The final report should give the owner a usable record for BCA submission, repair planning, contractor briefing, and comparison during the next inspection cycle.
When Is a Facade Inspection Report Required in Singapore?
A facade inspection report is required after BCA issues a Periodic Façade Inspection notice to the building owner. The PFI regime applies to buildings that are more than 20 years old and more than 13 metres tall, unless excluded.
The building owner must appoint a Competent Person to carry out the inspection and submit the report. The Competent Person is a Professional Engineer or Registered Architect with the required Certificate in Façade Inspection.
A Facade Inspector may assist with inspection work under the Competent Person’s direct supervision and control. However, the Competent Person remains responsible for the inspection methodology, findings, final assessment, report endorsement, and certification.
Once BCA issues the façade inspection notice, the owner, contractor, drone operator, or technology provider cannot prepare or certify the report in place of the appointed Competent Person.
From October 2025, additional requirements also apply to the appointment and duties of Facade Inspectors. In particular, the Competent Person must ensure that the appointed Facade Inspector is not conflicted by association with the building owner, builder, façade works contractor, or their associates. The Facade Inspector must also carry out inspection duties with reasonable diligence according to the Competent Person’s instructions.

How Inspection Evidence Is Collected
A facade inspection report should show the inspection method, evidence collected, inspection coverage, and areas checked. In Singapore, the visual inspection covers the full façade, while close-range inspection must cover at least 10% of the surface area of each elevation.
Full Visual Inspection
Full visual inspection is a visual survey of the entire building façade from ground level or other suitable vantage points.
The report should include full elevation photos, far views, medium-range views, and close-up photos where visible defects are observed. This stage records visible signs such as cracks, stains, spalling concrete, loose finishes, displaced façade elements, corrosion, bulging, misalignment, or other signs of façade deterioration.
Wide photos are important because they show where each defect sits on the building face. Without elevation-level context, the owner may see the defect but not know its exact location or how it relates to the wider façade system.
Close-Range Inspection
Close-range inspection checks selected façade areas in more detail. The minimum coverage is at least 10% of the surface area of each elevation, so the report should show the inspected areas, the calculation used, and the location of each checked zone.
This stage is intended to detect defects that may not be clear from full visual inspection alone. Common checks include hollowness, delamination, debonding, loose fixings, cracked façade elements, failed supports, concealed corrosion, deteriorated brackets, and signs of displacement or dislodgement.
The report should also record the tools or techniques used. These may include tapping rods, rubber mallets, borescopes, scanning equipment, non-destructive testing methods, or other approved inspection technologies.
Close-range inspection areas should be selected based on the Competent Person’s assessment. Factors may include visible defects from the full visual inspection, previous inspection records, façade type, deterioration risk, and the level of human traffic below the façade.
Full Façade Investigation
A full façade investigation may be required where the Competent Person identifies extensive, systemic, or severe defects. Examples include widespread loose panels or tiles, bulging plaster across multiple locations, missing or failed anchorages, extensive corrosion, or other conditions that may affect façade integrity.
Where the Competent Person assesses that a full façade investigation is necessary, an application must be made to the Commissioner of Building Control. This should be supported by an interim report and a proposed investigation scope.
The investigation scope may include design review, material testing, structural checks, localised removal of selected façade elements, laboratory tests, or closer inspection of concealed supports and connections.
Drones, AI, and Inspection Technology
Drones, AI, thermography, robotic tapping, and automated scanning improve how façade evidence is captured and organised. In H3 Zoom’s selected inspection workflows, technology has supported up to 70% lower inspection costs and up to 90% faster turnaround.
For a facade inspection report, the value is not just speed. Drone and AI-assisted inspection workflows can produce clearer elevation photos, mapped defect locations, structured image records, and faster review of repeated façade issues across large buildings.
The final assessment is still in the hands of the Competent Person. Technology supports evidence capture, defect mapping, and documentation, but it does not replace professional judgement or report certification.
What a Facade Inspection Report Must Include
A facade inspection report should show the building scope, inspection dates, checked areas, defect locations, photos, condition classification, repair actions, and Competent Person certification.
A report made mostly of photographs, with little technical assessment, does not serve the purpose of Periodic Façade Inspection. The report must be clear enough for the owner, BCA, consultants, and contractors to understand what was inspected, what was found, where it was found, how serious it is, and what action is required.
Photo Evidence and Defect Mapping
Photos should show more than damaged areas. The report should include full elevation views, medium-range shots, and close-up defect photos.
Each photo should connect to a location, drawing, elevation mark, or defect record. Without that link, the owner sees the problem but cannot confirm exactly where it is or what work is needed.
Effective defect mapping should answer four questions:
- Where is the defect?
- What type of defect was found?
- What evidence supports the finding?
- What action is required?
This is especially important for large developments, high-rise buildings, mixed façade systems, and buildings with repeated defect types across multiple elevations.
Assessment and Repair Actions
The Competent Person should classify the condition of each façade type or façade system as Safe, Require Repair, or Unsafe.
For defects or façade areas marked Require Repair or Unsafe, the report should state the repair method, proposed materials, precautionary measures, and timeframe. Where immediate safety control is required, this should be clearly identified.
For structural defects or repair works involving structural elements, additional engineering advice or approvals may be required before repair works commence.
Certification
The report should be signed and endorsed by the appointed Competent Person. This confirms that the inspection and report were completed under the required process.
Without proper Competent Person certification, the document is not a complete facade inspection report for BCA submission.
How Findings Are Classified
In Singapore’s Periodic Façade Inspection guidance, façade conditions are grouped into three classifications: Safe, Require Repair, and Unsafe.
Safe
A Safe classification does not mean the façade should be ignored until the next inspection. The report should still record the façade type, location, photos, and inspection evidence so the condition can be compared during the next inspection cycle.
Require Repair
Require Repair applies when the façade condition needs corrective work but does not pose imminent danger. Examples may include loose finishes, early corrosion, cracked façade elements, debonded tiles, deteriorated sealants, or defects that may worsen without repair.
The report should state the repair location, proposed repair method, materials, precautionary measures, and timeframe.
Unsafe
Unsafe applies when the façade condition is dangerous and needs immediate attention. This may include loose, unstable, severely corroded, displaced, or falling façade elements, along with signs of serious connection failure.
The report should state the safety measures needed before repair work starts. Measures may include removing loose elements, cordoning off affected areas, installing protective hoarding, restricting access, or carrying out urgent repair.
The classification should appear with the defect location, inspection evidence, risk level, and recommended action. It should not sit only in a photo caption.

What Happens After a Facade Inspection Report Is Submitted?
After a facade inspection report is submitted, the building owner should use it to guide facade repair planning, safety control, further investigation, record keeping, and the next inspection cycle.
Review the Report Findings
The owner should review the defect locations, photo evidence, classifications, and recommended actions. This shows which areas need no immediate repair, planned repair, immediate control, or deeper investigation.
Plan Repairs or Safety Measures
For repair findings, the report becomes the working reference for contractors, engineers, and facilities teams. The defect location, photo evidence, classification, and recommended repair method should define the repair scope.
Where immediate safety control is required, the owner should act before non-urgent repair work is planned. The report should state which areas need temporary control, urgent repair, or closer investigation.
Complete and Document the Work
After repair work is completed, the owner should keep repair photos, contractor records, material details, test records, and certification where required. These records show what was repaired and how the defect was addressed.
Keep the Report for the Next Inspection Cycle
The submitted report should not be treated as a one-time document. It should link inspection findings to repair decisions, completed work, and the next façade inspection cycle.
A clear report makes it easier to compare whether defects have stabilised, worsened, or reappeared over time.
What Building Owners Should Prepare Before Inspection
Building owners should prepare drawings, past reports, repair records, known façade issues, and access details before inspection starts. These records help the Competent Person verify the building scope, select close-range inspection areas, and prepare a clearer facade inspection report.
The owner or facilities team should also identify areas with high human traffic below the façade. These areas carry higher safety risk when loose panels, tiles, brackets, or other façade elements are found above entrances, exits, walkways, and gathering areas.
For drone-assisted facade inspection, the owner should prepare access permissions, flight restrictions, building contact points, and site rules that affect image capture. These details reduce delays and help the inspection team collect complete photo evidence.
The goal is to provide the Competent Person with complete and accurate information before the inspection begins. Drawings, past reports, repair records, known issues, and access details make the final report easier to verify, repair from, and compare during the next inspection cycle.
Common Facade Inspection Report Issues to Avoid
A poorly prepared facade inspection report creates gaps in the repair scope, audit trail, and submission record.
The main issue is not report length. A report is only effective when each defect is clearly linked to its location, supporting evidence, classification, and recommended repair action.
Technology-assisted inspection follows the same reporting requirements. Drone imagery, AI-assisted defect detection, thermal scans, and other digital outputs must still be linked to defect locations, inspection records, and professional assessment. Raw image sets alone do not constitute a complete facade inspection report.
Conclusion
A complete facade inspection report records more than visible defects. It should show inspection coverage, photo evidence, defect locations, condition classifications, repair recommendations, and Competent Person certification.
For building owners, the report should remain useful after submission. It links each finding to repair scope, safety decisions, completed work, and next-cycle comparison, so teams know what was found, what was repaired, and what still needs attention.
For asset owners and inspection teams, H3 Zoom turns inspection data into mapped defect records, structured evidence, and report-ready documentation that supports defect verification, repair planning, and long-term façade condition tracking.
The main issue is not report length. A report is effective only when each finding is clearly linked to its location, supporting evidence, classification, and recommended repair action.
Technology-assisted inspection follows the same reporting principles. Drone imagery, AI-assisted defect detection, thermal scans, robotic tapping outputs, and other digital records must still be linked to defect locations, inspection records, and professional assessment. Raw image sets alone do not constitute a complete facade inspection report.
How H3 Zoom Supports Facade Inspection Reporting
H3 Zoom helps asset owners, managing agents, consultants, and inspection teams turn façade inspection data into structured, traceable, and report-ready evidence.
Our platform supports:
- elevation-based image organisation;
- mapped defect locations;
- structured defect records;
- AI-assisted defect detection and review;
- photo evidence management;
- inspection workflow tracking;
- repair planning support; and
- long-term façade condition comparison.
For building owners, this means inspection records are easier to verify, repair from, and revisit during future inspection cycles.
For Competent Persons and inspection teams, H3 Zoom supports evidence capture, defect mapping, and documentation workflows while keeping the final professional assessment and certification with the appointed Competent Person.
Conclusion
A complete facade inspection report records more than visible defects. It should show inspection coverage, photo evidence, defect locations, condition classifications, repair recommendations, precautionary measures, and Competent Person certification.
For building owners, the report should remain useful after submission. It should link each finding to repair scope, safety decisions, completed work, and next-cycle comparison, so teams know what was found, what was repaired, and what still needs attention.
For asset owners and inspection teams, H3 Zoom’s facade inspection platform turns inspection data into mapped defect records, structured evidence, and report-ready documentation that supports defect verification, repair planning, and long-term façade condition tracking.
FAQ
Can a facade inspection report be prepared if old drawings are missing?
Yes, but the missing records should be made clear. The building owner should tell the Competent Person early and provide any available records, such as previous reports, repair records, maintenance logs, photos, or contractor documents.
What happens if some façade areas cannot be inspected?
The report should state which areas were not inspected and why. Access limits, blocked views, unsafe access, tenant restrictions, or site constraints should be recorded so the inspection record is clear.
Does a facade inspection report include repair costs?
A facade inspection report should include repair recommendations, repair methods, materials, precautions, and timeframe. It does not have to function as a contractor quotation unless pricing is included as part of a separate repair scope.
Can the report be used to brief contractors?
Yes. The report can help contractors understand defect locations, repair priorities, photo evidence, and recommended methods. Contractors may still need a site visit, detailed repair specifications, access planning, and material confirmation before starting work.
Does a Safe classification mean no future maintenance is needed?
No. Safe means the inspected façade element does not need repair at the time of inspection and is unlikely to become unsafe before the next cycle. The owner should still keep inspection records and continue normal façade maintenance.